Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works. Home construction will commence after civil construction is completed.
Comments
** For any further enquiries regarding construction of your townhome, please feel free to contact your respective Building Coordinator.
UPDATE - 18 December 2024
Welcome to the December 2024 Construction Update for Habitas Aurora! Below you will find the latest information in relation to construction progress on site.
Metricon Homes, is making great progress on your townhome, The link below provides access to the most recent video showcasing the progress being made. This information has also been uploaded to the Habitas Connect portal.
Habitas Aurora Construction Update Video - November 2024
HABITAS CONNECT PORTAL UPDATE
Development Victoria is committed to assisting their purchasers by providing clear communication on the milestones that will occur in the upcoming months to your handover.
As the first step, we have recently completed some updates made to the Habitas Connect portal. This includes changes to the last milestones displayed on the “Home Construction Progress” bar chart.
As a separate feature of the updated Habitas Connect portal, we have introduced the “Settlement and Handover Process” bar chart, which indicates the key milestones as part of your upcoming settlement and handover journey.
The new “Settlement and Handover Process” bar chart can be found on your respective lot group page. Please hover over the milestones for more details.
In the coming weeks, we will also be adding key information, as and when applicable, about your home by introducing the “Key Documents” section on the Habitas Connect portal. This will include uploading a more detailed explanation of the Settlement and Handover process, so please keep an eye out.
A more detailed summary on the status of works across the project is provided below:
Lots 81 - 89
Complete: Cabinetry, Tiling, Painting and Cladding
Underway: Landscape Hardscape
Next: House Clean
Lots 73 - 80
Complete: Painting, Tiling and Cladding
Underway: Internal Carpentry Fit-Off and Shower Screens Installation
Next: Flooring (Timber and Carpet) Installed
Lots 55 - 64
Complete: Roofing and Brickwork, Plaster
Underway: Cabinetry and Fix Carpentry
Next: Internal Painting and External Cladding
Lots 49 - 54
Complete: Frames, Lock-Up and Roofing
Underway: Brickwork and Plaster Installation
Next: Cabinetry Installation
Lots 68 - 71
Complete: Cabinetry and Fix Carpentry
Underway: Tiling, Painting and Cladding to commence
Next: Electrical, Plumbing and Carpentry Fit-Offs
Should you have any enquiries on the progress of construction or your home, please get in touch with your nominated Building Coordinator at Metricon Homes.
We also take this time to remind you that the Habitas Aurora development is an active construction site and access to lots is not permitted due to safety reasons.
We look forward to bringing you our next update in February/March 2025.
UPDATE - 1 October 2024
Welcome to the October 2024 Construction Update for Habitas Aurora! Below you will find the latest information in relation to construction progress on site.
Metricon Homes, is making great progress on your townhome, The link below provides access to the most recent video showcasing the progress being made.
Habitas Aurora Construction Update Video - September 2024
A more detailed summary on the status of works across the project is provided below:
Lots 81 - 89
- Complete: Slabs, Frames, Lock up and Roofing
- Underway: Plaster, Fix and Cabinetry
- Next: Painting, Tiling and External cladding
Lots 73 - 80
- Complete: Slabs & Frames
- Underway: Lock-up & Roofing
- Next: Plaster, Fix and Cabinetry
Lots 55 - 64
- Complete: Slabs
- Underway: Frames
- Next: Lock-up and Roofing
Lots 49 - 54
- Complete: Slabs
- Underway: Frames
- Next: Lock-up and Roofing
Lots 65 - 72
- Complete: Slabs
- Underway: Frames
- Next: Lock-up and Roofing
We also take this time to remind you that the Habitas Aurora development is an active construction site and access to lots is not permitted due to safety reasons.
We look forward to bringing you our next update in November/December 2024.
UPDATE - AUGUST 2024
Welcome to the August 2024 Construction Update for Habitas Aurora! Below you will find the latest information in relation to construction progress on site.
Metricon Homes, is making great progress on your townhome. The link below provides access to the most recent video showcasing the progress being made. This information has also been uploaded to the Habitas Connect portal.
Construction Progress Video - August 2024
A more detailed summary on the status of works across the project is provided below:
Lots 81 - 89
- Complete: Slabs and Frames
- Underway: Lock-up and Roofing
- Next: Fascia and Guttering
Lots 73 - 80
- Complete: Slabs and Frames
- Underway: Lock-up
- Next: Roofing, Fascia and Guttering
Lots 55 - 64
- Complete: Slab Footings
- Underway: Installation of inground services
- Next: Slab boxing and pouring
Lots 49 - 54
- Complete: Slab Footings
- Underway: Installation of inground services
- Next: Slab boxing and pouring
Lots 65 - 72
- Complete: Installation of inground services and slab footings
- Underway: Slab boxing and pouring
Landscape Enhancement Works
In addition to housing construction, we are pleased to advise that landscape enhancement works are underway on the Habitas Woodland Conservation Reserve. These works include installation of dedicated seating nodes, feature bollard fencing and educational signage, providing the community with greater access to, and understanding of, the rich ecological and environment values of the site.
Should you have any enquiries on the progress of construction of your home, please get in touch with your nominated Building Coordinator at Metricon Homes.
We also take this time to remind you that the Habitas Aurora development is an active construction site and access to lots is not permitted due to safety reasons.
We look forward to bringing you our next update in September 2024.