Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
complete
Completion of the construction works. Home construction will commence after civil construction is completed.
Comments
** For any further enquiries regarding construction of your townhome, please feel free to contact your respective Building Coordinator.
UPDATE - 18 December 2024
Welcome to the December 2024 Construction Update for Habitas Aurora! Below you will find the latest information in relation to construction progress on site.
SOHO Living, is making great progress on your townhome, The link below provides access to the most recent video showcasing the progress being made. This information has also been uploaded to the Habitas Connect portal.
Habitas Aurora Construction Update Video - November 2024
HABITAS CONNECT PORTAL UPDATE
Development Victoria is committed to assisting their purchasers by providing clear communication on the milestones that will occur in the upcoming months to your handover.
As the first step, we have recently completed some updates made to the Habitas Connect portal. This includes changes to the last milestones displayed on the “Home Construction Progress” bar chart.
As a separate feature of the updated Habitas Connect portal, we have introduced the “Settlement and Handover Process” bar chart, which indicates the key milestones as part of your upcoming settlement and handover journey.
The new “Settlement and Handover Process” bar chart can be found on your respective lot group page. Please hover over the milestones for more details.
In the coming weeks, we will also be adding key information, as and when applicable, about your home by introducing the “Key Documents” section on the Habitas Connect portal. This will include uploading a more detailed explanation of the Settlement and Handover process, so please keep an eye out.
A more detailed summary on the status of works across the project is provided below:
Lots 1 - 7
Complete: Tiling and External Cladding
Underway: Landscaping and Pre-settlement inspections
Next: Settlement & Handover
Lots 13 - 18
Complete: Cabinetry
Underway: Painting and Tiling
Next: Plumbing/Electrical fit off, Flooring
Lots 18 - 24
Complete: Cabinetry
Underway: Plaster
Next: Painting and Tiling
Lots 8 - 12
Complete: Roofing and Plaster
Underway: Pre-paint, Fix Carpentry and Cabinetry
Next: Tiling, Plumbing/Electrical fit off, Flooring
Lots 25 - 36
Complete: In-ground services and Slab boxing
Underway: Frames
Next: Lock-up and Roofing
Lots 37 - 39
Complete: Frames
Underway: Lock-up and Roofing
Next: Electrical Rough-ins and Plaster
Lots 43 - 48
Complete: Slab
Underway: Frames
Next: Lock-up and Roofing
Should you have any enquiries on the progress of construction or your home, please get in touch with your nominated Building Coordinator at SOHO Living.
We also take this time to remind you that the Habitas Aurora development is an active construction site and access to lots is not permitted due to safety reasons.
We look forward to bringing you our next update in February/March 2025.