Lots 28-29,31

When will my lot be ready?

Civil construction

Complete

Statement of Compliance

Complete

Land Title Registration

Complete

Townhouse Construction

In progress

Estimated Settlement Timeframe

Early-Mid 2025

Comments

UPDATE  -  1 October 2024

Welcome to the October 2024 Construction Update for Habitas Aurora! Below you will find the latest information in relation to construction progress on site.

SOHO Living, is making great progress on your townhome, The link below provides access to the most recent video showcasing the progress being made.

Habitas Aurora Construction Update Video - September 2024

A more detailed summary on the status of works across the project is provided below:

Lots 1 - 7
- Complete: Lock-up and Roofing
- Underway: Plaster, Fix and Cabinetry
- Next: Paint, Tiling and External Cladding

Lots 13 - 24
- Complete: Slabs
- Underway: Frames and Roof truss installation
- Next: Lock-up and Roofing

Lots 8 -12
- Complete: Slabs
- Underway: Frames
- Next: Lock-up and Roofing

Lots 25 - 36
- Complete: In-ground services
- Underway: Slab boxing
- Next: Slabs pour

Lots 37 - 48
- Complete: Slab
- Underway: Frames
- Next: Lock-up and Roofing

We also take this time to remind you that the Habitas Aurora development is an active construction site and access to lots is not permitted due to safety reasons.

We look forward to bringing you our next update in November/December 2024.

UPDATE -  AUGUST 2024

Welcome to the August 2024 Construction Update for Habitas Aurora! Below you will find the latest information in relation to construction progress on site.

SOHO Living, is making great progress on your townhome. The link below provides access to the most recent video showcasing the progress being made. This information has also been uploaded to the Habitas Connect portal.

Construction  Progress Video  - August  2024

A more detailed summary on the status of works across the project is provided below:

Lots 13 - 24
- Complete: Slabs
- Underway: Frames and roof truss installation
- Next: Lock-up

Lots 8 - 12
- Complete: Slabs
- Underway: Frames

Lots 25 - 36
- Complete: Site cut
- Underway: Installation of in-ground services
- Next: Slab boxing and pouring

Lots 37 - 48
- Complete: Slab Footings
- Underway: Installation of In-ground services
- Next: Slab boxing and pouring

Landscape Enhancement Works

In addition to housing construction, we are pleased to advise that landscape enhancement works are underway on the Habitas Woodland Conservation Reserve. These works include installation of dedicated seating nodes, feature bollard fencing and educational signage, providing the community with greater access to, and understanding of, the rich ecological and environment values of the site.

Should you have any enquiries on the progress of construction of your home, please email the team at Habitas Aurora.

We also take this time to remind you that the Habitas Aurora development is an active construction site and access to lots is not permitted due to safety reasons.

We look forward to bringing you our next update in September 2024.

Civil Construction Progress Video - November 2023

Civil Construction Progress Video May 2023

Civil Construction Progress Video April 2023 Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works. Home construction will commence after civil construction is completed.